performanceonaproject.Itisequaltotheearnedvalue(EV)minustheactualcost(AC).Thecost
varianceattheendoftheprojectwillbethedifferencebetweenthebudgetatcompletion(BAC)and
theactualamountspent.TheCVisparticularlycriticalbecauseitindicatestherelationshipof physical
performancetothecostsspent.NegativeCVisoftendifficultfortheprojecttorecover. EquationCV
=EV–AC


TheSVandCVvaluescanbeconvertedtoefficiencyindicatorstoreflectthecostandschedule
performanceofanyprojectforcomparisonagainstallotherprojectsorwithinaportfolioofprojects.
Thevariancesareusefulfordeterminingprojectstatus.


...


Costperformanceindex.Thecostperformanceindex(CPI)is ameasureofthecostefficiencyof
budgetedresources,expressedasaratioofearnedvaluetoactualcost.Itisconsideredthemost
criticalEVMmetricandmeasuresthecostefficiencyfortheworkcompleted.ACPIvalueoflessthan



  1. 0 indicatesacostoverrunfor workcompleted.A CPIvalue greater than 1. 0 indicatesacost
    underrunofperformancetodate.TheCPIisequaltotheratiooftheEVtotheAC.Theindicesare
    usefulfordeterminingprojectstatusandprovidingabasisforestimatingprojectcostandschedule
    outcome.Equation:CPI=EV/AC


Thethreeparametersofplannedvalue,earnedvalue,andactualcostcanbemonitoredand reported
onbothaperiod-by-periodbasis(typicallyweeklyormonthly)andonacumulativebasis. Figure 7 –
12 usesS-curvestodisplayEVdataforaprojectthatisperformingoverbudgetandbehindschedule.


120.Answer:C.


PMBOK® Guide, page 261 , Section 7. 4. 2. 2


DataAnalysis


Earned valueanalysis (EVA),sometimes calledearned value management (EVM),compares the
performancemeasurementbaselinetotheactualscheduleandcostperformance.EVMintegrates
the scope baseline with the cost baseline and schedule baseline to form the performance
measurementbaseline.EVMdevelopsandmonitorsthreekeydimensionsforeachworkpackage and
controlaccount.


121.Answer:D.


PMBOK® Guide, pages 260 – 265 , Section 7. 4. 2. 2 ; and Figure 7 – 12


Earned Value Management


...


Variances from the approved baseline will also be


Monitored:


Schedulevariance.Schedulevariance(SV)isameasureofscheduleperformanceexpressedasthe
differencebetweentheearnedvalueandtheplannedvalue.Itistheamountbywhichtheprojectis
aheadorbehindtheplanneddeliverydate,atagivenpointintime.Itisameasureofschedule
performanceonaproject.Itisequaltotheearnedvalue(EV)minustheplannedvalue(PV).TheEVM
schedulevarianceisausefulmetricinthatitcanindicatewhenaprojectisfallingbehindoris ahead
ofitsbaseline schedule.TheEVMschedulevariancewillultimatelyequal zerowhenthe