http://www.alsenosy.com | http://www.professionalengineers.us
3.Bidderconferences
4.Dataanalysis
o Proposal evaluation
5.Negotiation
209.Answer:B.
PMBOK® Guide, page 471 , Section12.1.1.6
Organizational Process Assets
Cost-reimbursablecontracts.Thiscategoryofcontractinvolvespayments(costreimbursements)to
thesellerforalllegitimateactualcostsincurredforcompletedwork,plusafeerepresentingseller
profit.Thistypeshouldbeusedifthescopeofworkisexpectedtochangesignificantlyduringthe
executionofthecontract.
Variations can include:
Costplusfixedfee(CPFF).Thesellerisreimbursedforallallowablecostsforperformingthecontract
workandreceivesafixed-feepaymentcalculatedasapercentageoftheinitialestimatedproject
costs.Feeamountsdonotchangeunlesstheprojectscopechanges.
210.Answer:C.
PMBOK® Guide, page 479 , Section12.1.3.6
Make-or-BuyDecisions
Amake-or-buyanalysisresultsinadecisionastowhetherparticularworkcanbestbeaccomplished
bytheprojectteamorneedstobepurchasedfromoutsidesources.
211.Answer:B.
PMBOK® Guide, page 488 , Section12.2.2.5
Interpersonal and Team Skills
Interpersonalandteamskillsthatcanbeusedforthisprocessincludenegotiation.Negotiationisa
discussionaimedatteachingaagreement.Procurementnegotiationclarifiesthestructure,rights,
andobligationsofthepartiesandothertermsofthepurchasessothatmutualagreementcanbe
reachedprior tosigningthecontract.Finaldocumentlanguagereflects allagreementsreached.
Negotiationconcludeswith asignedcontractdocument orother formalagreementthatcanbe
executedbybothbuyerandseller.Thenegotiationshouldbeledbyamemberoftheprocurement
teamthathasthe authorityto signcontracts.Theprojectmanager andother membersofthe
projectmanagementteammaybepresentduringnegotiationtoprovideassistanceasneeded.