- Consider the following information about the duration of an activity :
Calculated expected (tE) = 5 weeks.
Optimistic (tO) = 4 weeks.
Pessimistic (tP) = 8 weeks.
Using the beta distribution and the three-point estimating approach, the Most likely (tM) activity
durationis:
A.4.0weeks.
B.4.5weeks.
C.5.0weeks.
D.6.0weeks.
- Consider the following three estimates for the duration of an activity :
Optimistic (tO) = 6 weeks.
Most likely (tM) = 9 weeks.
Pessimistic (tP) = 15 weeks.
Using the triangular distribution, the calculated Expected activity duration (tE)is:
A.10.0weeks.
B.10.5weeks.
C. 1 1. 5 weeks.
D.12.0weeks.
- Anactivityinaprojectnetworkhasthefollowingcharacteristics: ES= 5 ,EF
= 10 , and LF = 14. Therefore, LS.=
A. 9.0weeks.
B.10.0weeks.
C. 11.0weeks.
D.12.0weeks.