  1. Consider the following information about the duration of an activity :


Calculated expected (tE) = 5 weeks.


Optimistic (tO) = 4 weeks.

Pessimistic (tP) = 8 weeks.

Using the beta distribution and the three-point estimating approach, the Most likely (tM) activity
durationis:


A.4.0weeks.


B.4.5weeks.


C.5.0weeks.


D.6.0weeks.



  1. Consider the following three estimates for the duration of an activity :


Optimistic (tO) = 6 weeks.


Most likely (tM) = 9 weeks.

Pessimistic (tP) = 15 weeks.

Using the triangular distribution, the calculated Expected activity duration (tE)is:


A.10.0weeks.


B.10.5weeks.


C. 1 1. 5 weeks.


D.12.0weeks.



  1. Anactivityinaprojectnetworkhasthefollowingcharacteristics: ES= 5 ,EF
    = 10 , and LF = 14. Therefore, LS.=


A. 9.0weeks.


B.10.0weeks.


C. 11.0weeks.


D.12.0weeks.