100.The Control Schedule process for aproject :


A. Focuses on starting the project earlier than scheduled to help mitigate schedule risk and to
achieve the approved schedulebaseline.
B. Is the process of monitoring the status of the project to update the project schedule and
managing changes to the schedulebaseline.
C. Is concerned mainly with activities that are on the criticalpath.
D. Should focus primarily on activities that are difficult to carryout.