  1. The project life cycle is best definedas :


A. The continuum of a project lifecycle.
B. The phases that a product or service passes through from its start to itscompletion.
C. The series of phases that a project passes through from its start tocompletion.
D. The various ways requirements and plans are brought from a project charter tocompletion.

228.Projects following more of the adaptive side of the project life cycle most
closely follow the pattern of :


A. Sequential, iteration-based phases and continuous overlappingphases.
B. Sequential, iteration-based phases and sequential nonoverlappingphases.
C. Continuous overlapping phases and agile-basedphases.
D. Agile-based phases and sequential, iteration-based phases.

229.All of the following are Process Groups Inadaptive environments EXCEPT:


A. Planning ProcessGroup.
B. Monitoring and Controlling ProcessGroup
C. Scope Management Process Group I). Closing ProcessGroup.

230.Iterative, agile, and adaptive approaches track, review, and regulate
progress and performance bymaintaining:


A. A A detailed to-dolist
B. Abacklog.
C. A work breakdownstructure.
D. Workpackages.

231.life cycles develop a set of high-level plans for the initial requirements


and progressively elaborate requirements to an appropriate level of detail for
the planning cycle.


A. Predictive
B. Adaptive
C. Plan-driven
D. Program