C. Projectscanintersectwithoperationsatvariouspointsduringtheproductlifecycle.Ateach
point,deliverablesandknowledgearetransferredbetweentheprojectandoperationsfor
implementationofthedeliveredwork.
D. Becauseoftheirtemporarynature,projectscannothelpachieveanorganization’slong-term
goals.Therefore,strategicactivitiesintheorganizationcanbegenerallyaddressedwithinthe
organization'snormaloperations.

7.Your job responsibility is to align components (projects, programs,or
related operations) to the organizational strategy, organized into portfolios
orsubsidiary portfolios to optimize project or programobjectives,
dependencies,costs, timelines, benefits, resources, and risks. This is known as:


A. Components management.
B. Processmanagement.
C. Programmanagement.
D. Portfoliomanagement.

8.The PMBOK® Guide is the standard for:


A. Managing all projects all of the time,
B. Managing all projects most of thetime.
C. Managing most projects most of thetime.
D. Managing some projects some of thetime.

9.The collection of generally sequential and sometimes overlapping project
phases, whose name and number are determined by the management and
control needs of the organization or organizations involved in the project, is
known asthe :


A. Projectwaterfall.
B. Project lifecycle.
C. Project lifestages.
D. Project Management Process Groups.

10.All of the following are true about project phases and the project life cycle
EXCEPT:


A. Stakeholderinfluences,risk,anduncertaintyaregreatestatthestartoftheproject.These
factorsdecreaseoverthelifeoftheproject.
B. Theabilitytoinfluencethefinalcharacteristicsoftheproject'sproduct,withoutsignificantly
impactingcost,ishighestatthestartoftheprojectanddecreasesastheprojectprogresses
towardcompletion.
C. Thecost ofchanges andcorrecting errors typically increasessubstantially as the project
approachescompletion.
D. Costandstaffinglevelsaregenerallysteadythroughouttheprojectlifecycle.

11.All of the following statements about the project life cycle and the product
life cycle are trueEXCEPT: