Building Construction Handbook, Eighth Edition

(Nancy Kaufman) #1

Further Quality Procedures (Structure) ~



  • Provision of insulation to be continuous. Gaps are
    unacceptable and if allowed to occur will invalidate the
    insulation value by thermal bridging.

  • Junctions at elements of construction (wall/floor, wall/roof)
    to receive particular attention with regard to continuity of
    insulation.

  • Openings in walls for windows and doors to be adequately
    treated with insulating cavity closers.


Further Quality Procedures (Energy Consumption) ~



  • Hot water and heating systems to be fully commissioned on
    completion and controls set with regard for comfort, health
    and economic use.

  • As part of the commissioning process, the sealed heating
    system should be flushed out and filled with a proprietary
    additive diluted in accordance with the manufacturer's
    guidance.


This is necessary to enhance system performance by resisting
corrosion, scaling and freezing.



  • A certificate confirming system commissioning and water
    treatment should be available for the dwelling occupant. This
    document should be accompanied with component
    manufacturer's operating and maintenance instructions.


Note: Commissioning of heating installations and the issue of
certificates is by a qualified `competent person'' as recognised by the appropriate body, i.e. CAPITA GROUP, OFTEC or HETAS. CAPITA GROUP ~Gas Safe Register' of Installers (formerly CORGI).
OFTEC ~ Oil Firing Technical Association for the Petroleum
Industry.
HETAS ~ Solid Fuel. Heating Equipment Testing and Approval Scheme.


Thermal Insulation, U-Value Objectives for New Dwellings