of the gates equals to the Peak Hour Operations /2, as shown in Table 6- 11 , the peak hour
operations that can be accommodated by the runway was determined in Section 6.2.3.
Table 6 - 11 Capacity of the Gates at Peak Hour
Phase Year
Peak Hour
Operations
Capacity of Gates
at Peak Hour
2027 - 2034 2034 53 27
2035 - 2042 2042 53 27
2043 - 2050 2050 105 53
Equation 6-2 is used to estimate the number of recommended gates:
Gate time supplied ≥ gate time demanded
훍퐤퐍퐤 ≥ E ( 퐓퐠)퐂퐠 (6-2)
Where:
μk= gate utilization factor.
Nk= number of gates available.
E (Tg)= expected value of the gate occupancy time demanded.
Cg= capacity of the gates per hour.
- Assume gate utilization factor 80%, the gate occupancy time demanded 50 min.