Chapter 7Introduction to the law of contract
If the court holds that the sum is liquidated damages, it
will be enforced irrespective of whether the actual loss is
greater or smaller.
1 The damage can include sums for financial loss,
damage to property, personal injury and distress, dis-
appointment and upset caused to the claimant.
255
(a) to what breaches of contract the clause applies;
(b) what amount is payable on breach;
(c) what amount would be payable if the claim was
brought under common law;
(d) what were the parties’ reasons for agreeing the
clause;
(e) whether the party who claims the clause is a penalty
can show that it was imposed as a deterrent and that
it does not constitute a genuine pre-estimate of loss.
M & J Polymers Ltdv Imerys Minerals
Ltd(2008)
The Commercial Court had to decide whether a ‘take or
pay’ clause in a contract for the supply of chemical dis-
persants amounted to a penalty. A ‘take or pay’ clause is
a provision which obliges a buyer to pay for a minimum
quantity of products, irrespective of whether that quantity
is ordered. Burton J held that the clause in question was
not a penalty, although as a matter of principle the rule
against penalties could apply to ‘take and pay’ clauses.
Based on the facts of the case, he was satisfied that the
clause was commercially justifiable, was not oppressive,
was entered into freely by parties of comparable bargain-
ing power, and did not have the predominant purpose of
deterring a breach of contract or amount to a provision
‘in terrorem’.
Cellulose Acetate Silk Co Ltdv Widnes
Foundry Ltd(1933)
Widnes Foundry agreed to pay £20 for every week of
delay in completing a plant for the Silk Co. The work was
completed 30 weeks late. The Silk Co claimed that its
actual losses amounted to nearly £6,000. It was held that
Widnes Foundry was only liable to pay £20 a week (i.e.
£600) as agreed.
Unliquidated damages
The aim of unliquidated damages is to put the injured
party in the position he would have been in if the con-
tract had been carried out properly. Damages are
designed to compensate for loss. If no loss has been suf-
fered, the court will only award nominal damages,
which is a small sum to mark the fact that there had been
a breach of contract. The courts observe the following
guidelines when awarding damages:
Jarvisv Swans Tours(1973)
Jarvis, a solicitor, paid £63.45 for a two-week winter
sports holiday in Switzerland. The Swans Tours brochure
promised a ‘house party’ atmosphere at the hotel, a bar
which would be open several evenings a week and a
host who spoke English. The holiday was a considerable
disappointment: in the second week, he was the only
guest in the hotel and no one else could speak English.
The bar was only open one evening and the skiing was
disappointing. The Court of Appeal awarded him £125 to
compensate for ‘the loss of entertainment and enjoy-
ment which he was promised’.
Exemplary or punitive damages designed to punish the
party in breach are not normally awarded in contract.
2 The injured party cannot necessarily recover dam-
ages for every kind of loss which he has suffered.The
breach might have caused a chain reaction of events to
occur. Clearly, there is a point beyond which the damage
becomes too remote from the original breach. The rules
relating to remoteness of damage were laid down in
Hadleyv Baxendale(1854). The injured party may recover
damages for:
■loss which has resulted naturally and in the ordinary
course of events from the defendant’s breach; and
■the loss which, although not a natural consequence of
the defendant’s breach, was in the minds of the par-
ties when the contract was made.
The practical application of these rules can be seen in
the following cases.
Victoria Laundry (Windsor) Ltdv Newman
Industries Ltd(1949)
The claimant company of launderers and dyers wished to
expand its business and, for this purpose, had ordered a
new boiler from the defendants. The boiler was damaged
during the course of its removal and, as a result, there was
a five-month delay in delivery. The claimant claimed:
(a) damages of £16 per week for the loss of profits it
would have made on the planned expansion of the
laundry business; and