Chapter 7Introduction to the law of contract
Breaches of contract for the sale of goods are subject
to the rules laid down in the Sale of Goods Act 1979.
They will be considered in more detail in Chapter 10.
Although as a general rule damages for breach of con-
tract should be assessed as at the date of the breach, there
are exceptions, as can be illustrated by this recent case.
4 Once a breach of contract has occurred, the innoc-
ent party is under a duty to mitigate (minimise) his
loss.He cannot stand back and allow the loss to get
worse. A seller whose goods have been rejected, for
example, must attempt to get the best possible price for
them elsewhere. The claimant will not be able to recover
for that part of the loss which has resulted from his fail-
ure to mitigate.
257
The trial judge held that, even though the pool was not
as deep as specified in the contract, it was still safe for
diving. There was no evidence that the value of the pool
had decreased because of the shortfall in depth. The
only way of curing the defect would be to demolish the
pool and build a new one at a cost of £21,560. The judge
doubted whether Mr Forsyth would build a new pool as
it would not be reasonable to do so. The judge awarded
£2,500 for loss of amenity. The Court of Appeal reversed
the decision of the trial judge and awarded Mr Forsyth
the full cost of achieving a cure, i.e. £21,560. The House
of Lords reversed the decision of the Court of Appeal
and reinstated the trial judge’s original decision. Their
Lordships took the view that if the cost of cure was
unreasonable, the measure of damages should be the
difference in value. Although the pool was probably no
less valuable, Mr Forsyth was entitled to some compen-
sation for his loss of satisfaction.
into account. (ii) Although, as a general rule, damages
should be assessed as at the date of the breach, the rule
was subject to exceptions and should not be applied
mechanistically, and there may be another date which
might be used as the basis for compensating the injured
party.
Golden Strait Corporationv Nippon
Yusen Kubishka Kaisha (The Golden
Victory)(2007)
In 1998 GSC chartered a tanker (The Golden Victory) to
NYKK for a period of seven years. The charterparty con-
tained a clause which entitled either party to terminate
the contract if war broke out between any two or more
countries which included the United States, the United
Kingdom and Iraq. In 2001 NYKK repudiated the charter
by redelivering the tanker to the owners GSC. There
were nearly four years left to run on the charter and GSC
claimed damages for the remaining term of the contract.
NYKK argued that they would have been entitled to ter-
minate the contract in March 2003 when the second Gulf
War broke out and therefore damages should only be
assessed up to this (earlier) date. The House of Lords
held (by 3:2) that (i) damages for breach of contract
are designed to compensate the injured party for the
loss of his contractual bargain and he should be placed
in the position he would have been in had the contract
been performed. However, if the contract would have
terminated earlier (because of the occurrence of an event
anticipated in the contract), then this should be taken
Bracev Calder(1895)
The claimant was dismissed by his employers but offered
immediate re-engagement on the same terms and con-
ditions as before. He refused the offer and instead sued
to recover the salary he would have received for the
remaining 19 months of his two-year contract. It was held
that the claimant should have mitigated the loss by accept-
ing the employer’s reasonable offer of re-employment.
He was entitled to nominal damages only.
The duty to mitigate any loss does not arise until there
has been a breach of contract which the injured party
has accepted as a breach.
White and Carter (Councils) Ltdv
McGregor(1961)
The claimants were advertising agents who supplied
local authorities with litter bins on which they displayed
advertisements. The defendant entered into a contract
with the claimants to advertise his garage in this way for
a three-year period. Later the same day, however, the
defendant cancelled the contract. The claimants refused
to accept the cancellation and proceeded to carry out the
contract by preparing advertising plates and attaching
them to litter bins. The claimants sued for the full amount
due under the contract. The House of Lords upheld their
claim. The claimants were under no duty to mitigate their
loss because they had not accepted the defendant’s
breach.
Comment. Although the reasoning in this case is logical,
the result, as Lord Keith put it, is ‘startling’. However, a