Fundamentals of Financial Management (Concise 6th Edition)

(lu) #1
Chapter 12 Cash Flow Estimation and Risk Analysis 369

12-2 ANALYSIS OF AN EXPANSION PROJECT


In Chapter 11, we analyzed two projects, S and L. We were given the cash! ows
and used them to illustrate how the NPV, IRR, MIRR, and payback are calculated.
Now we demonstrate how cash! ows are actually estimated, using our old
Project S to demonstrate the procedure. We explain the process in Table 12-1. Look
at it as we discuss the analysis. Note that the dollars are in thousands; we omitted


Tabl e 12 - 1 Cash Flow Estimation and Analysis for Expansion Project S

1 2 3 4 5 6 7 8 9

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34

A B C D E F G H I

Investment Outlays at Time = 0

Net Cash Flows Over the Project’s Life

Equipment
Net WC

Unit sales
Sales price
Variable cost per unit
Sales revenues = Units! Price
Variable costs = Units! Cost/unit
Fixed operating costs except depr’n
Depreciation: Accelerated from table below
Total operating costs
EBIT (or operating income)
Taxes on operating income 40%
After-tax project operating income
Add back depreciation
Salvage value (taxed as ordinary income)
Tax on salvage value (SV is taxed at 40%)
Recovery of net working capital
Project net cash !ows (Time Line)

537
$10.00
$5.092
$5,370
2,735
2,000
297
$5,032
$338
135
$203
297

520
$10.00
$5.391
$5,200
2,803
2,000
405
$5,208
-$8
-3
-$5
405

505
$10.00
$5.228
$5,050
2,640
2,000
135
$4,775
$275
110
$165
135

490
$10.00
$6.106
$4,900
2,992
2,000
63
$5,055
-$155
-62
-$93
63
50
-20
100
$100

-$900
-100

-$1,000

0 1 2 3 4

$500 $400 $300
Depreciation

Alternative depreciation

Project Evaluation @ WACC = 10%

Accelerated
Rate
Depreciation
Straight line
Rate
Depreciation

1
33%
$297

45%
$405

15%
$135

7%
$63

Cost: $900

Cost: $900

Accelerated
NPV
IRR
MIRR
Payback

$78.82
14.489%
12.106%
2.33

=NPV(D29,F22:I22)+E22
=IRR(E22:I22)
=MIRR(E22:I22,D29,D29)
=G2+(-E22-F22-G22)/H22

$64.44
13.437%
11.731%
2.60

Formulas Straight line

2 3 4

25%
$225

25%
$225

25%
$225

25%
$225


  1. If the "rm owned assets that would be used for the project but would be sold if the project is not accepted, the
    after-tax value of those assets would be shown as an ”opportunity cost” in the ”Investment Outlays” section.

  2. If this project would reduce sales and cash !ows from one of the "rm's other divisions, then the after-tax cannibalization
    e#ect, or ”externality,” would be deducted from the net cash !ows shown on Row 22.

  3. Accelerated depreciation rates are set by Congress. We show the approximate rates for a 4-year asset in 2008.
    Companies also have the option of using straight-line depreciation. Under IRS rules, salvage value is not deducted when
    establishing the depreciable basis. However, if a salvage payment is received, it is called a recapture of depreciation
    and is taxed at the 40% rate.

  4. If the "rm had previously incurred costs associated with this project, but those costs could not be recovered
    regardless of whether this project is accepted, then they are ”sunk costs” and should not enter the analysis.


35

36

37

38
Free download pdf