A-14 Appendix A Solutions to Self-Test Questions and Problems
NPV Pro! les for Projects X and YNPV
($)4,0002,0003,0001,000!1,0005 10 15 20
0NPVCrossover Rate = 6.2%
NPVCost of Capital
(%)YXY IRRx
IRRCost of Capital NPVX NPVY
0% $3,500 $4,000
4 2,545 2,705
8 1,707 1,592
12 966 631
16 307 (206)
18 5 (585)Chapter 12
a. Estimated investment requirements:Price ($55,000)
Installation ( 10,000)
Change in net working capital ( 2,000)
Total investment ($67,000)b. Depreciation schedule:
Equipment cost! $65,000; MACRS 3-year classYEARS
1 2 3
MACRS depreciation rates 33% 45% 15%
Equipment depreciation expense $21,450 $29,250 $9,750Note that the remaining book value of the equipment at the end of the project’s
life is 0.07 & $65,000! $4,550.