technical NOTES

(Project Pridr) #1
S. N. Buildings (M3)RCC R/f Steel(MT) R/f Factor(Kg/m3)
1 Boundary Wall 2,923 225 77
2 Plant Flooring 12,436 315 25
3 Plant Roads & Drains
Total - Infra 15,359 540 35
Grand Total 86,239 12,645 147
1 Clinkerisation Section 44,915 7,932 177
2 Grinding Section 18,715 3,257 174
3 Common Facilities 7,250 916 126
4 Infrastructure 15,359 540 35
Grand Total 86,239 12,645 147

G. IU 2: 4500 TPD, Integrated Unit at Andhra Pradesh


S. N. Buildings (M3)RCC TMT(MT) R/f Factor(Kg/m3)
Clinkerisation Section
1 Lime Stone Stock pile 3,078 358 116
2 Coal Stockpile 3,719 445 120
3 Corrective/Additive stockpile 3,590 413 115
4 Blending Silo 2,348 498 212
5 Unburnt Clinker Hopper/Silo 334 52 157
6 Clinker Silo 5,307 801 151
7 Preheater Tower + compressor 6,983 1,592 228
8 Kiln Piers & TA Duct 2,328 177 76
9 Cooler + Cooler ESP + DPC 2,453 323 132
10 Raw Material Hopper 598 101 168
11 Raw Mill Building 4,650 556 120
12 Raw Mil Bag House 2,515 364 145
13 Dust Transport System 1,995 333 167
14 Wagon Tippler 1,802 185 102
15 Truck Tippler 1,094 165 151
16 Coal Mill + Coal Mill Hopper 2,710 241 89
17 LS Crusher 2,786 269 97
18 Coal Crusher & conveying 240 21 89
19 Belt Conveyors + Transfer Towers 2,635 203 77