technical NOTES

(Project Pridr) #1
S. N. Buildings (M3)RCC TMT(MT) R/f Factor(Kg/m3)
2 Plant Roads & Drains 7,129 - -
3 Culverts 275 - -
Total - Infra 15,503 - -
Grand Total 1,29,363 - -
1 Clinkerisation Section 82,185 - -
2 Grinding Section 22,975 - -
3 Common Facilities 8,700 - -
4 Infrastructure 15,503 - -
Grand Total 1,29,363 - -

J. IU 5: 5500 TPD, Integrated Unit at Rajasthan


S. N. Buildings (M3)RCC R/f Steel(MT) R/f Factor(Kg/m3)
Clinkerisation Section
1 Lime Stone Stock pile 2,339 129 55
2 Coal Stockpile 1,662 83 50
3 Corrective/Additive stockpile 2,060 94 46
4 Unburnt Clinker Hopper/Silo 486 69 142
5 Clinker Silo 7,107 947 133
6 Preheater Tower + compressor 6,067 1,414 233
7 Kiln Piers & TA Duct 1,814 110 61
8 Cooler + Cooler ESP + DPC 2,166 289 133
9 Raw Material Hopper 703 92 131
10 Raw Mill Building 2,643 405 153
11 Raw Mil Bag House 1,342 149 111
12 Wagon Tippler 2,919 292 100
13 Coal Mill + Coal Mill Hopper 1,528 172 113
14 LS Crusher 3,663 372 102
15 CCBC 660 72 109
16 Belt Conveyors + Transfer Towers 3,050 332 109
17 Over Head Cable Gallery & Cable Trenches 1,215 69 57
18 Switch yard and load centres 1,975 214 108
19 Clinker Wagon Loading system 1,037 237 229