S. N. Plant
Config.
Plant
Cap.
(TPD)
Railway Siding
Infra
RCC Factor
/ Ton
of plant
capacity
Estimated
Qty. for
RCC (in
M3)
TMT
Factor
/ Ton
of plant
capacity
Estimated
Qty. for
TMT (in
MT)
Remarks
3 CU 10000 Wagon tippler
with Raw materi-
al Unloading and
Silo Loading for
Clinker Loading
12 120000 1.62 16200
4 CU 6000 NA 12 72000 1.62 9720
5 CU 6000 Wagon tippler
with raw material
unloading
15 90000 2.025 12150
6 CU 6000 Wagon tippler
with Raw materi-
al Unloading and
Silo Loading for
Clinker Loading
16 96000 2.16 12960
7 GU 300 NA 100 30000 12 3600 Shall be
valid for
250 and
275 TPH
also
8 GU 300 Wagon tippler
with raw material
unloading
160 48000 19.2 5760 Shall be
valid for
250 and
275 TPH
also
9 GU 300 Wagon tippler
with Raw materi-
al Unloading and
Silo Loading for
Cement Loading
180 54000 21.6 6480 Shall be
valid for
250 and
275 TPH
also
- Note: Operating cost shall be validated with present condition.
Note: Above factors and quantity estimates are for initial rough order estimation
purpose only. Detailed estimates shall depend of various important factors like
location, soil bearing capacity, plant layout, plant configuration, seismic and wind
zones, infrastructure requirements etc.
Various other factors which has been analyzed from the final data of Projects can
be generally used as under for estimation:
- Excavation quantity in m3 : 3.0 times the RCC quantity in cum
- Shuttering quantity in m2 : 3.7 times the RCC quantity in cum
- PCC quantity in m3 : 0.25 times the RCC quantity in cum
- Miscellaneous work in a Project i.e. plaster, painting, Grouting, structural steel
for civil, insert, pocket, Water proofing, door windows ~10% of the total Project
cost