482 ENGINEERING THERMODYNAMICS
dharm
\M-therm\Th10-2.pm5
Example 10.19. It is required to design an air-conditioning system for an industrial proc-
ess for the following hot and wet summer conditions :
Outdoor conditions ...... 32ºC DBT and 65% R.H.
Required air inlet conditions ...... 25ºC DBT and 60% R.H.
Amount of free air circulated ...... 250 m^3 /min.
Coil dew temperature ...... 13ºC.
The required condition is achieved by first cooling and dehumidifying and then by heating.
Calculate the following :
(i)The cooling capacity of the cooling coil and its by-pass factor.
(ii)Heating capacity of the heating coil in kW and surface temperature of the heating coil if
the by-pass factor is 0.3.
(iii)The mass of water vapour removed per hour.
Solve this problem with the use of psychrometric chart.
Solution. Refer Fig. 10.23.
Fig. 10.23
l Locate the points ‘1’, ‘5’ and ‘3’ as shown on psychrometric chart.
l Join the line 1-5.
l Draw constant specific humidity line through ‘3’ which cuts the line 1-5 at point ‘2’.
The point ‘2’ is located in this way.
From psychrometric chart :
h 1 = 82.5 kJ/kg, h 2 = 47.5 kJ/kg
h 3 = 55.7 kJ/kg, h 5 = 36.6 kJ/kg