Thus the load to be carried by anchorage in shale 1100 – 72 1028 kN. This load can be
resisted by an anchor cable made up from seven 15.2 mm 7-wire Dyform strands. The
breaking load of each strand is 300 kN. Therefore
which is satisfactory. The approximate overall diameter of the 7-strand cable is 45 mm.
Therefore for an allowablebond stress between steel and grout of 1.0 N/mm^2 :
Drill the cable hole to 9 m and provide an unwrapped and cleaned bond length of 7 m with
compression fittings swaged on to the lower end. The cable can be fed down a 150 mm
borehole for which,
which is satisfactory for a strong shale (Table 6.3). The stress is not excessive if the anchors
are stressed to 1.5 times the working load during installation.
From Figure 6.17a, the volume of a rock cone with a 30 half angle lifted by single anchor
cable is 0.35 93 255 m^3. The submerged weight of the rock cone 1.39.81
255/1 000 3.25 MN.
The anchorage of the whole dock floor requires 70 lines of anchors (at right-angles to the
centre-line of the dock) and 20 ranks of anchors ( parallel to the centre-line of the dock) to
form the 3 m square grid. Therefore in Figure 6.17b, N 70, M 20, and P S 3 m.
From Figure 6.17a, m/L n/L 0.57, and therefore, m n 0.57 9 5.1 m. Then
P/n s/m 0.59 so that, from Figure 6.17b,. Because
(P/n)^2 (S/m)^22 0.59^2 0.7 is less than 4, there is composite overlapping of the rock
cones, and the charts are not valid. The intersecting cones represent a rock volume roughly
estimated to be 69 3 19 3 6 70 794 m^3.
The sum giving the total force resisting uplift is thus as follows:
Weight of dock floor 237.3 MN
Submerged weight of soft clay 791.1 MN
Submerged weight of anchored rock 902.8 MN
Total 1931.2 MN
70 794 1.3 9.81
1000
210 ^60 8.0 0.8 9.81
1000
210 ^60 0.8 2.4 9.81
1000
VnVcVmVc 0.45
Factor of safety against uplift 3.25
1.03
3.1 (which is satisfactory)
working bond stress between rock and grout 1028 ^1000
150 7.0 1000
0.31 N/mm^2
required bond length of cable 1 0281 000
45 1.01 000
7.3 m
working load 1 028
7 300
0.49breaking load of strand
Piles to resist uplift and lateral loading 359