swelling forces on the inner sides of beams they should not be left in contact with the clay.
After casting the concrete has been completed, the clay should be cut back as shown in
Figure 7.15. The space between the side of the beam and the cut-back of the excavation is
left empty, or is only loosely backfilled.
Ground beams are provided to act as ties or compression members between adjacent pile
caps, so providing the required restraint against sidesway or buckling of the piles under lat-
eral or eccentric loading (see Section 7.5). Ground beams and pile capping beams may have
to withstand horizontal loading from the soil due to the tendency to movement of vertical
piles under lateral loading. They may also be subjected to bending in a vertical direction due
to differential settlement between adjacent groups of piles.
It may be permissible to allow the passive resistance of the soil against the sides of pile
caps and ground beams to supplement the resistance of the piles to lateral loading. However,
in clay soils the ground will shrink away from the sides of shallow members in dry weather
conditions. Trenching for building services alongside pile caps must also be considered a
possibility. In any case quite appreciable yielding of the soil must take place before its
passive resistance is fully mobilized. This movement may be sufficient to cause the failure
in bending of vertical piles.
The superimposed loading on the ground beams or pile capping beams is transferred to
the piles by bonding the longitudinal reinforcing steel to the beams into the pile caps.
However, it is not good practice to carry the longitudinal steel through holes burned in the
projecting parts of steel piles. It is quite likely that the pile head will have deviated from the
correct position and it may be impossible to bend the beam reinforcing bars over a sufficient
horizontal distance to pass through the holes in the steel pile without causing complications
Structural design of piles and pile groups 395
Reinforcement lapped with capping beam
steel and extended downwards to anchor
into zone of non-swelling clay
Layer of special low-density
foamed plastic or 'Clayboard'
Beam under
cross wall
150 mm void
Precast r.c suspended floor
Dry bed joint
280 mm
Damp-proof course
Cranked vent
Ground level
R.c capping beam
Face of excavation cut back
and space loosely filled or
left void
Bored and cast
in place pile
Figure 7.15Design of pile capping beam for swelling clay soils.