226 Highway Engineering
Concrete discharged to
loose surcharge level
Bottom course trimmed
and compacted
Top course of concrete
spread to final level
Surface protected by travelling
tentage
Dowel bars vibrated into
place
Longitudinal and transverse
joint crack inducers fixed
Side-tipping vehicle
Side-tipping vehicle
Separation membrane
laid
Longitudinal and transverse joint
crack inducers fixed
Bottom course
spreader
Bottom course
compactor
Dowel bar
placer
Top course
spreader
Top course trimmed,
compacted and screeded,
longitudinal joint formed and
sealed
Top course
compactor
Joint former Transverse joint formed
Surface screeded to
Final finisher final level
(diagonal beam)
Surface texture applied
(surface wire-brushed or
grooved). Curing membrane
applied.
Texturing and curing
sprayer
Travelling
tentage
Figure 7.19Diagrammatic representation of fixed-form paving train.