WORKED EXAMPLES 111
Worked Example 2.1
The outline profile of an earthfill embankment is illustrated in Fig. 2.18.
ROCK grout cut-off
k (see part (b))
Fig. 2.18 Worked example 2.1 (Fig. 2.11)
GEOTECHNICAL DATA
The foundation alluvium has a permeability (antisotropic) of kh 4 kv
1 105 ms^1. The design effective permeability of the grouted cut-off
zone,kc2.5 107 ms^1.
- Draw the foundation flownet without a grouted cut-off in position
and calculate seepage flow, Q 0 , in m^3 m^1 day^1. - Determine the width, t, of grouted cut-off zone required to achieve a
designEQof 70% and compute the corresponding value of EH. - Determine the corresponding porewater pressure at point X in m
head.
Solution
- Transform factor1/2. See flownet on Fig. 2.11: NF/Nd3/16.5
0.18.k(alluvium)(kvkh)1/20.5 105 ms^1. Therefore
Q 0 (0.5 105 )20(0.18)(243600) (2.15)
1.55 m^3 m^1 day^1.
- With EQset at 70%, Q0.30Q 0 0.47 m^3 m^1 day^1. Therefore
‘equivalent’Nf/Nd0.055.
(0.18)0.47
1.55