DHARM
678 GEOTECHNICAL ENGINEERING
R.C. column
Column pedestal
Reinforcing steel
Pile cap
Pile
Fig. 16.13 Pile cap for a R.C. column
The spacing of piles in a group depends upon a number of factors such as the overlap-
ping of stresses of adjacent piles, cost of foundation and the desired efficiency of the pile group.
Pile
Isobar Isobar
(c) Widely spaced group of piles
(without zones of stress overlap)
Stress isobars
(a) Signal pile
Pile
Pile cap
Pile
Stress isobar
for single pile zone of overlap(highly-stressed)
Stress isobar of
group of piles
(b) Closely spaced group of piles
(with zones of stress overlap)
Fig. 16.14 Stress isobars of single pile and groups of piles