Engineering Economic Analysis

(Chris Devlin) #1
308 UNCERTAINTY IN FUTURE EVENTS

than on the other two. This equation was developed as an approximation with the beta
distribution.

Optimistic value + 4(Most likely value) + Pessimistic value

Mean value= 6 (10-1)


This approach is illustrated in Example 10-4.


Solve Example 10-3 by using Equation 10-1. Compute the resulting mean rate of return.


.SOLUTION


Compute the mean for each parameter:

Mean cost =[950+ 4 x 1000 + 1150]/6=1016.7

Mean net annual benefit- [210 + 4 x 200 + 170]/6=196.7


Mean useful life=[12 + 4 x 10 + 8]/6=10.0


Mean salvage life=100/6=16.7


Compute the mean rate of return:

PW of cost =PW of benefit


$1016.7 =196.7(j>/A,IRRbeta,10) + 16.7(j>IF,IRRbeta, 10)

IRRbeta= 14.2%


Iioo


Example 10-3 gave a most likely rate of return (15.1%) that differed from the mean
rate of return (14.2%) computed in Example 10-4. These values are different because the
former is based exclusively on the most likely values and the latter takes into account the
variability of the parameters.
In examining the data, we see that the pessimistic values are further away from the most
likely values than are the optimistic values. This is a common occurrence. For example, a
savings of 10 to 20% may be the maximum possible, but a cost overrun can be 50%, 100%,
or even more. This causes the resulting weighted mean values to be less favorable than the
most likely values. As a result, the mean rate of return, in this example, is less than the rate
of return based on the most likely values. '

PROBABILITY


We all have used probabilities. For example, what is the probability of getting a "head"
when flipping a coin? Using a model that assumes that the coin is fair, both the head and
tail outcomes occur with a probability of 50%, orY2'This probability is the likelihood {'
Free download pdf