Telecommunications Design 19
o. Room environmental controls is adequate and operating to maintain proper temperature
and humidity levels.
- This list shall have columns that assign responsibility to the appropriate trade, completion date and
room for comments.
B. As-Builts:
- Provide a hard copy floor plan print to be placed inside each telecommunications room. This shall
be a clean drawing illustrating only telecommunications infrastructure with updated quantities that
accurately reflect everything that was installed during the project. All labeling will be visible on this
drawing to indicate locations that correlate to the patch panels inside the telecommunications room.
C. Cabling Run Excel Document:
- Provide a formatted excel schedule that contains information for all copper cabling on the project.
The schedule shall have the following columns with all associated information filled in:
a. Building Name/Number
b. Room Name (location of data jack)
c. IDF Closet #
d. Wirerun (jack label)
e. Pairs
f. Termination Style (568B)
g. Cable Type (Category 6, 6A, 6A foil)
h. Function (Data, Camera, Wall Phone, ELMS Reader, RTLS, WAP) - Provide a formatted excel schedule that contains information for all fiber optic cabling on the
project. The schedule shall have the following columns with all associated information filled in:
a. Fiber
b. Source Building
c. Source Room
d. Source FB (Fiber Box or Shelf)
e. Source FB Panel (Splice panel)
f. Destination Building
g. Destination Room
h. Destination FB (Fiber Box or Shelf)
i. Destination FB Panel (Splice panel)
j. Fiber Type (Singlemode, Multimode OM4)
k. Length
l. Strand Count
November 1, 2016