example:
Project B has a NPV of -$20,000. We can issue
debt at 8% to finance the project. The new debt
has a PV Tax Shield of $60,000. Assume that
Project B is your only option.
Project NPV = - 20,000
Stock issue cost = 60,000
Adjusted NPV 40,000
do the project
Adjusted Present Value