paimio sanatorium

(Jacob Rumans) #1

Hankkija’s report stated that establishing a separate power plant for the sanatorium


would require the acquisition of larger boilers and if the sanatorium relied completely


on its own power station with no reserve capacity purchased from outside, two boilers


and generators would be necessary. Hankkija did not discuss the profitability of a sep-


arate power plant to any degree, as there was not enough information to back up such


calculations.^960 At this stage, Lounais-Suomen Sähkö reduced its offer to the level


suggested by the Building Board^961 , and the Building Board accepted the tariffs.^962 An


agreement was reached at the end of 1931.^963 The sanatorium substation and part of the


network were powered on in January 1933.^964 Aalto did not actively participate in the


discussion on the electricity contract or the method of electricity production.


Established in 1912, Lounais-Suomen Sähkö was a leading operator in the region,


but its competitive situation changed radically in 1929, when a State-owned power


station was completed in Koroinen and the company lost its biggest client, the City


of Turku. Many customers asked the company in 1930 to scrap its basic charge and


960 The letter of Keskusosuusliike Hankkija to engineer Kilpi, October 16, 1931. Attachment A. Building Board October
17, 1931, Section 9. PSA.
961 In case of a long term contract, the electric company would insist on having a paragraph that would allow it to take
into account the currency fluctuation. Attachment B. Lounais-Suomen Sähkö’s letter to the Building Board, dated
October 17, 1931. Building Board October 17, 1931, Section 9. PSA.
962 Building Board October 17, 1931, Section 9. PSA.
963 Building Committee December 23, 1931, Section 1. PSA.
964 Building Committee January 1, 1933, Section 1. PSA.

Fig. 3.6.2a. View of the transmission room. Photo No. 50-003-405. AAM.

Free download pdf