Chapter 15. Complete a Thorough Root Cause Analysis 351
Figure 15-9. Stack chart of work element times
In addition to the time required for each element, it’s useful to understand
the problem visually by depicting the flow of work (Figure 15-10). This pictorial
flow is captured on the Standardized Work Sheet (Chapter 6).
Machine
Parts
Supply
Inspection
Finished
Parts
1
2
Machine
Start
3
4
5
6
Figure 15-10. Visual depiction of work flow