The Engineer

(Grace) #1

Timeline 348



  • January. Tesla brought the Roadster to
    Arvidsjaur, Sweden, to see if it could
    survive winter conditions

  • February. 205 employees. Tesla began to
    build a validation prototype (VP), where
    they took everything they learned from
    the engineering prototype. Tesla says it
    will build a $35 million plant in Albu-
    querque, to produce the Model S

  • March. 230 employees and they finished
    the VP 1

  • April. Raised more money - a series D
    round led by Elon Musk, Technology
    Partners, and Vantage Point

  • June. Tesla’s motor factory in Taiwan
    was finished and it began producing parts

  • July. A new transmission was finished

  • August. Tesla finished the VP 10. CEO
    Martin Eberhard was replaced by Tesla
    investor Michael Marks, who would work
    as an interim-CEO until Tesla found a
    long-term CEO

  • September. Tesla delayed the launch of
    the Roadster because they needed more
    time to test its durability

  • October. It turned out that also the new
    transmission failed in the durability test.
    Tesla needed yet another transmission

  • November. Martin Eberhard had to leave
    the company