off-the-shelf roof trusses and having them
extend to these areas to construct the
building’s superstructure the design produced
significant cost savings of around £20,000-
30,000, and reduced construction
time considerably.
Integra House took nine months in
total to build; three months longer than
anticipated because there was no main
contractor. Instead, a separate contractor
was used for the groundworks, another for
the joinery, and Deveci got hands-on, doing
the plumbing and electricity himself.
“Workmanship was difficult, and a bit
more time-intensive,” Deveci admits.
In addition to specifying budgetary
constraints, the client was, says Deveci,
“very involved.” Weekly meetings were
arranged over coffee to which “she
would always bring a magazine and try
to hint that there were certain aspects
that she liked and didn’t like.” The
architect compiled a wish-list of features
which included a wood-burning stove
and far-reaching views from the
kitchen and living area over the
Aberdeenshire countryside.
In order to retain the monolithic aesthetic
of the building provided by the timber
cladding, Deveci also specified a drainage
system whereby rainwater flows through the
timber cladding on the roof via thin slits,
down a corrugated iron roof beneath and
into a hidden gutter. “I didn’t want a plastic
or metal gutter; it would have been a much
less elegant solution.”
There were already agricultural sheds and
stables around the site, and the ageing of the
materials plus the shape of the plan make the
house look “almost agricultural in nature,”
says Deveci, “particularly to the north of the
scheme, where there are very few openings in
the house’s external envelope.”
In terms of acoustics, Integra House is
well-suited to the building’s intended
function. “My client is single – if there were
others in the house then there may have been
some challenges.” According to the architect,
the double height spaces tend to create some
constraints when it comes to acoustic
performance: “It’s best to have some kind of
mass in an all timber-framed house.” The
internal organisation of the building was
impacted by the gable ends in that first floor
space was particularly tight due to truss wind
load calculations, and there was also a need
to be conscious of the direction of the stairs
leading up to the attic space, which had to
run parallel to the trusses.
Green on green
The truss is made from standard
structural grade soft wood, the external
cladding is 45 mm thick Siberian larch
“which does not require external treatment,”
and the insulation is partly wood fibre. which
TIMBER
The building’s entire structure and insulation is
composed of timber
Using off-the-shelf roof
trusses and extending them
to construct the building’s
superstructure produced
significant cost savings
PROJECT REPORT: SELFBUILD & CUSTOM BUILD PROJECTS 39
ADF JUNE 2019 WWW.ARCHITECTSDATAFILE.CO.UK