Canal Boat – July 2018

(Barré) #1

canalboat.co.uk Canal Boat July 2018 63


diverted where its course had been used for
the town’s bypass and former rubbish tip
(albeit a diversionary route had been
reserved).
So Phase 1 was chosen as the subject of the
first major funding bid. But an initial
approach to the Heritage Lottery Fund for a
grant in the region of £22m to provide the
bulk of the funding received a reply which
might be summarised along the lines of
“Sorry but we don’t have the resources for a
grant of that size: come back with a bid for
half that amount, and we’ll see what we can
do.”
This left the canal restorers with a
dilemma: if they could only restore half of
Phase 1, which half should it be? To many
canal boaters the answer seemed obvious:
opening up the western end from Saul, and
then using that as a springboard for further
progress eastwards to Stroud and beyond,
made a lot more sense than opening an
isolated length limited to local boats and
small craft which would then need to be
linked to the national network at a later date.
But the HLF and other potential funders
weren’t primarily interested in
narrowboating. The HLF’s interest was
heritage – and there was relatively little
heritage work to be done in the western four
miles. Five of the six surviving historic locks
on this length had already at least been partly
restored, and the work still to be done was
more about finding engineering solutions to
the M5, A38 and rail crossings and building a
mile of new canal with two new locks to
replace the missing length. Likewise the other
likely funders, the regional development
agency, Stroud District Council and other
local authorities, were more interested in
urban regeneration and long-term job
creation – of which there also wasn’t a great
deal on the western part.
By contrast the eastern six miles of Phase 1,
from Stonehouse to Brimscombe, included
numerous surviving locks and bridges to
restore, and ran through a former mill valley
with a great deal of regeneration potential and
immediate benefits for local people. As such it
ticked all the boxes for the big funders – and
so, to a certain amount of disappointment
among boating folks, the Trust plumped for
the eastern section, dubbed ‘Phase 1a’. And
sure enough, the funders supported it to the
tune of over £20m in total.
Fast forward a few years, and despite a few
wobbles along the way (including British
Waterways’ withdrawal from the
partnership; the need to drop the uppermost
length near Brimscombe when the economic
downturn meant that commercial
redevelopment of the Port was no longer
going to pay for it; and a much greater
volunteer involvement required to make up
for a funding shortfall), it’s now very nearly
complete. New main road bridges and
several smaller liftbridges have been built,
the Stroud diversion completed, nine locks

RESTORATION


So why should HLF fund this


length, when the wisdom some


years ago was that they would be put


off by the lack of heritage value?


A length of canal channel east of Whitminster
survives in fair condition but is weed-filled

The canal shares its route with the River Frome for
some distance near Whitminster
Free download pdf