Challenges
Environment was probably the biggest challenge for Mandylights,
located in the middle of the harbour with the crew ge ng blasted
by winds in excess of 70 Km an hour. Add to that salt spray and in
some loca ons the fixtures are only six metres away from the water.
“There was constant hammering from water and wind plus
Auckland has temperatures well into the 30 degree Celsius range so
you need UV protec on,” commented Richard. “Also, the
installa on has to last for ten years so exposed cables was a
massive considera on as well. On top of that, the Bridge is
constantly moving with the vibra ons from traffic.”
The outside lanes of the bridge were added a er the main structure
was built in 1959, with the four clip-on lanes added in 1969. In a
ma er of seconds, this road deck can move by up to a metre as the
load on the road decks above change.
Accessibility was difficult and crew had to be on top of their game
as environmental condi ons were also in play
Other technical challenges were access and many of the places
where lights were installed were incredibly difficult to get to. Rise
Pacific, a specialist rigging company from Sydney, designed and built
a completely unique access system to get the Mandylights crew
specifically to where they needed to go.
Fixture choice
From the beginning Richard was clear that he wanted to light the
Bridge with three types of LED fixtures in three very definite styles.
A wash light was required to light the internal structure of the
Bridge, a linear strip to outline the en re exterior perimeter of the
structure and finally, an LED dot fixture for the 170 diagonals and
ver cals under the Bridge.
“We wanted to highlight the internal structure of the Bridge by
ligh ng the girders and also poin ng some lights down to reflect off
the water,” explained Richard. “We wanted the most amount of
colour and reflec on we could, off the water to emphasize the
connec on with the water. With the linear strips we wanted to
outline the road deck and the arch as I don't think people realise
what an arced, sweeping shape it has. Finally, we used LED dots to
turn the outer girders of the bridge into what is effec vely a low res
video surface, made out of the bridge architecture itself.”
Mandylights looked at a few varia ons of applicable LED fixtures
but found they gravitated towards Mar n due to the reliability of
product and the incredible support offered by their Australian and
New Zealand distributor Show Technology. Over the years,
Mandylights has worked with Show Technology many mes and
cannot fault their service. Show Technology's Michael Gearin looked
a er Mandylights from the technical and sales end.
“We worked extremely closely with Mar n on this project as there
were many custom components needed, including a 505mm pitch
on the VC dots to allow for thermal expansion in the hot months,”
commented Michael. “Altera ons were needed for the steel to
expand and contract without ripping the ribbon tails out of the
fixtures on a hot day. A similar customiza on was needed for the
1,990mm Exterior PixLines to lower fixture count and make them a
prac cal size for the treacherous install; also considering thermal
expansion of course. Mar n were really suppor ve and fantas c to
deal with on such a massive undertaking, it was their largest LED
installa on to date with over 90,000 LEDs installed. Simply put,
there wasn't much that was off the shelf and they helped to tailor
their reliable products to meet our specific needs.”
“The fact that Show Technology has an Auckland office and were
able to support the project locally, was very important to us,”
explained Richard. “We had a very ght window for pitching this
project and to present the ini al crea ve response, and the fact
that we were able to turn up to the first pitch mee ng with actual
working samples of the products was really beneficial.”
Installa on process
Show Technology worked alongside Mandylights throughout the
en re installa on period allowing them to warehouse and prep the
fixtures in New Zealand and offer ongoing technical consults
throughout the project.
The installa on process took just over five months and Richard
commented that there were a lot of Work Health and Safety
restric ons to overcome. Due to high winds on the bridge there
were even a few weeks when the crew were unable to work
because some of the necessary equipment for the installa on on
the Bridge would not be safe over certain wind speeds.
INSTALLATION NEW ZEALAND