Above left to right:
The rst AIM-9
was red from
Raptor 02 on July
25, 2000. This
photo shows the
rst supersonic
ring on July 25,
2002, with Lt Col
Chris Short at the
controls of Raptor
- Lockheed
Martin/ Derk
Blanset
Fred Knox
conducts the rst
F-22 external fuel
tank jettison while
ying Raptor 02
on April 22, 2004.
Lockheed Martin/
Kevin Robertson
The F-22
carries a special
‘compressed-
carriage’ variant
of the AIM-120C,
developed to t
in the con ned
weapons bay of
the F-22. Lockheed
Martin/Tom
Reynolds
Lt Col Evan
Thomas
completed the rst
separation test
of a 1,000-pound
GBU-32 Joint
Direct Attack
Munition on April
23, 2004. This
was a later test in
December 2005
with Maj John
Teichert at the
controls for the
rst supersonic
guided release of
a JDAM. Lockheed
Martin/Darin Russell
Edwards
maintainers load
an inert AIM-120
during EMD work.
Note the aircraft
carries the F/A-
22 titles on the
vertical stabilisers.
USAF
A rare shot of
an EMD Raptor
carrying AIM-120
AMRAAMs on
the external wing
stations.
which joined the Combined Test Force at
Edwards in March 2000.
Delays in the delivery of the EMD
aircraft saw this phase being pushed to
the right, indeed it became clear that the
development test work would overlap
with the Dedicated Initial Operational Test
and Evaluation (DIOT&E) phase.
The rst EMD aircraft (4001) was
own hard and was retired in 2000. This
stemmed from the discovery of hairline
cracks in 4001 and 4002, although the
second aircraft resumed ight-testing.
MOVING FORWARD
The Edwards test work with the eventual
employment of nine EMD Raptors was
tied to the major procurement milestones.
All eyes were on meeting test points and
the Pentagon Defense Acquisition Board’s
decision to award an initial batch of LRIP
aircraft. The programme had to achieve
use of the Block 3.0 software, re the rst
AMRAAM and get aircraft 4004, 4005 and
4006 into the test programme.
In the event, the rst AIM-120C AMRAAM
shot came on October 24, 2000, and
aircraft 4006 ew in early 2001, but the
resulting decision to proceed with LRIP
was not taken until August 15, 2001, when
initial batch of 10 aircraft was approved.
Meanwhile, the PRTV aircraft were taking
shape. The rst of these ew on October
12, 2002. These aircraft were to be used
initially for DIOT&E, which was scheduled
to start in August 2002, but was delayed
until its commencement on April 29, 2004.
Such was the concurrency knock-on that
by this time, the rst aircraft had already
been delivered to the rst USAF squadron.
The 43rd Fighter Squadron, part of the
325th Fighter Wing, at Tyndall AFB, Florida,
received F-22A serial 01-4018/TY, on
September 26, 2003.
In the background, development test
work continued at Edwards. Avionics
issues including in- ight shut downs
were proving problematic, however on
December 27, 2005, the EMD phase was
concluded, by which time 12 combat-ready
F-22As had already been delivered!
RAPTOR^25
16-27 Metz First Flight C.indd 25 28/09/2017 14:53