The protracted timing of Increment 3.2B
meant that AIM-9X Sidewinder wasn’t
planned to be on the front line until
2017, so the USAF added a rudimentary
capability to carry the AIM-9X and
AIM-120D before Increment 3.2B is
completed. The AIM-120D was added
in Update 4, with the AIM-9X added in
Update 5, which hit the squadrons in 2015.In fact, according to the 2016 annual
report by the Director of Operational
Test and Evaluation, Increment 3.2B
developmental testing continued
throughout Fiscal Year 2016 but
experienced delays due to software
stability and performance shortfalls. It
said: ‘In-flight cockpit display blanking and
ESMS functionality deficiencies resultedThe 411th Flight Test Squadron brought
together an impressive gathering of
Raptors in August 2016 for a test project
combining development and operational
test, presumably linked to Increment
3.2B. Lt Col Randel Gordon, F-22 CTF
director and 411th FLTS commander, said
operational F-22s from the USAF come to
Edwards for testing occasionally, but that itwas ‘highly unusual’ to have eight total
Raptors at Edwards, including one being
serviced in the 411th FLTS hangar. The
photo is also unusual in that it shows Block
30 F-22A serial 07-4132 painted as 06-
4132, and specially marked for the 411th
FLTS commander. The aircraft is notable
in that it carries a wing-mounted AIM-120
AMRAAM on a twin launcher rail.GATHERING OF RAPTORS
in flight safety operating restrictions,
and required additional unanticipated
OFP [Operational Flight Program]
software releases and regression testing.
Consequently, the planned Air Force
Milestone C decision slipped from March
to August 2016.’ At Milestone C, the USAF
authorised the procurement of 35 of 71
planned hardware kits through low-rate
initial production (LRIP). The USAF said it
does not plan to procure the remaining
LRIP kits until it confirms progress in
resolving the deficiencies.
Reported flight-testing in September
2016 apparently showed improvement
with cockpit display stability; however,
ESMS deficiencies persisted. According
to the report, as of the end of FY16,
investigative efforts had not fully
ruled out the possible need for system
hardware design changes. It added:
‘Given the limited development progress
in FY16, it is unlikely that Increment 3.2B
developmental testing will complete
as planned at the end of April 2017,
or that IOT&E will begin as planned in
August 2017.’
Once the gremlins are ironed out, every
combat-coded F-22 from aircraft 03-4045
onwards will receive these upgrades,
according to Air Combat Command.
Another major issue still to be overcome
is the Raptor’s lack of helmet-mounted
display (HMD). Lockheed Martin planned
to add the Joint Helmet-Mounted Cueing
System (JHMCS), but this has never been
realised, for unknown reasons. In early
2014, the 422nd TES is known to haveLeft: Seven
Raptors sit
outside the
411th Flight Test
Squadron on
August 10, 2016.
USAF/Christian
Turner
Below: The F-22
production line
in Marietta.
Despite the
production
tooling having
been retained,
any talk of
building more
Raptors has
been quashed.
Lockheed Martin/
Eric Schulzinger(^96) RAPTOR
94-98 Latest test C.indd 96 28/09/2017 15:38