76 PROjECT PRIDE
• Preparation of unloading beds at a designated location
• Removal/grounding of power cables fouling in
transport track
• Readiness of 450T crane with unloading tools and
tackles
• Continuous GPS tracking of consignment location
(from the warehouse to site)
The preparation of approach roads and unloading beds