Dalmia DSP Success Story

(Project Pridr) #1

80 PROjECT PRIDE


132 kV substation work started in February 2019

As of February 2019 RCC completion was around 40,000
CuM and total fabrication completion was around 3,700
MT and erection was around 500 MT; the figures indicating
that it was still a long way to go. In the month of February
2019, FLSmidth E&I team had mobilized their contractor
and started the work of 132 kV substation, which was a
major event for the project, putting the pressure on the
other teams to speed up the work.
Main equipment like kiln shell, kiln support roller
assembly, bucket elevator parts, belt conveyor gearbox,
HRP base frame, HRP cylinder, HRP bearing assembly, coal
mill housing, deep pan conveyor parts, weigh feeders, and
other auxiliary materials were received at the site during
January–March 2019, many other critical items were under