Control Quality is generally performed before Validate Scope, although the two processes may be
performed inparallel.
- Answer: B.
PMBOK® Guide, page 162 , Section 5. 4. 3. 1
ScopeBaseline
WBSdictionary.TheWBSdictionaryisadocumentthatprovidesdetaileddeliverable,activity,and
schedulinginformationabouteachcomponentintheWBS.TheWBSdictionaryisadocumentthat
supportsthe WBS. Mostoftheinformation includedin theWBS dictionaryis createdby other
processesandadded tothisdocumentat alaterstage.Informationinthe WBSdictionary may
include,butisnotlimitedto:
o Code of accountidentifier,
o Description of work,
o Assumptions andconstraints,
o Responsible organization,
o Schedulemilestones,
o Associated scheduleactivities,
o Resourcesrequired,
o Cost estimates,
o Quality requirements,
o Acceptancecriteria,
o Technical references,and
o Agreement information.
- Answer: D.
PMBOK® Guide, pages 170 – 171 , Section 5. 6. 3 ; page 160 , Figure 5 – 14 ; pages 167 – 168 , Figure 5 –
17 and Figure 5 – 18
ControlScope:Outputs
1.Work performanceinformation.
2.Changerequests.
3.Project management planupdates:
o Scope managementplan.
o Scopebaseline.
o Schedulebaseline.
o Cost baseline.
- Project documentsupdates:
o Lessons learned register.