Control Quality is generally performed before Validate Scope, although the two processes may be
performed inparallel.



  1. Answer: B.


PMBOK® Guide, page 162 , Section 5. 4. 3. 1


ScopeBaseline


WBSdictionary.TheWBSdictionaryisadocumentthatprovidesdetaileddeliverable,activity,and
schedulinginformationabouteachcomponentintheWBS.TheWBSdictionaryisadocumentthat
supportsthe WBS. Mostoftheinformation includedin theWBS dictionaryis createdby other
processesandadded tothisdocumentat alaterstage.Informationinthe WBSdictionary may
include,butisnotlimitedto:


o Code of accountidentifier,


o Description of work,


o Assumptions andconstraints,


o Responsible organization,


o Schedulemilestones,


o Associated scheduleactivities,


o Resourcesrequired,


o Cost estimates,


o Quality requirements,


o Acceptancecriteria,


o Technical references,and


o Agreement information.



  1. Answer: D.


PMBOK® Guide, pages 170 – 171 , Section 5. 6. 3 ; page 160 , Figure 5 – 14 ; pages 167 – 168 , Figure 5 –
17 and Figure 5 – 18


ControlScope:Outputs


1.Work performanceinformation.


2.Changerequests.


3.Project management planupdates:


o Scope managementplan.


o Scopebaseline.


o Schedulebaseline.


o Cost baseline.



  1. Project documentsupdates:


o Lessons learned register.