+360-Questions-and-Answers-For-PMBOK-Guide-SIXTH -Edition

(khatib.arch2) #1
http://www.alsenosy.com | http://www.professionalengineers.us


  1. Answer: B.


PMBOK®Guide,page 338 ,Section 9. 4


DevelopTeam


Oneof themodels usedto describeteam developmentis the Tuckmanladder[ 19 , 20 ], which
includesfivestagesofdevelopmentthatteamsmaygothrough.Althoughitiscommonforthese
stagestooccurinorder,itisnotuncommonforateamtogetstuckinaparticularstageorregressto
anearlierstage.Projectswithteammemberswhoworkedtogetherinthepastmightskipastage.


o Forming.Thisphaseiswheretheteammembersmeetandlearnabouttheprojectandtheir
formalrolesandresponsibilities.Teammemberstendtobeindependentandnotasopeninthis
phase.
o Storming.Duringthisphase,theteambeginstoaddresstheprojectwork,technicaldecisions,
and the project management approach.If teammembers arenot collaborativeor open to
differingideasandperspectives,theenvironmentcanbecomecounterproductive.
o Norming.Inthisphase,teammembersbegintoworktogetherandadjusttheirworkhabitsand
behaviorstosupporttheteam.Theteammemberslearntotrustoneanother.
o Performing.Teamthatreachtheperformingstagefunctionasawell-organizedunit.Theyare
interdependentandworkthroughissuessmoothlyandeffectively.
o Adjourning.Inthisphase,theteamcompletestheworkandmovesonfromtheproject.This
typicallyoccurswhenstaffisreleasedfromtheprojectasdeliverablesarecompletedoraspart of
theCloseProjectorPhaseprocess.



  1. Answer: C.


PMBOK®Guide,pages 322 - 324 ,Section 9. 2. 1


EstimateActivityResources: Inputs


1.Project managementplan


2.Projectdocuments.


3.Enterprise environmentalfactors


4.Organizational processassets



  1. Answer:C.

Free download pdf