- Answer: C.
PMBOK® Guide, pages 411 - 412 , Section 11.2.1; and Figure 11 - 6
The Identify Risks process has the followinginputs:
Project managementplan
o Requirements management plan
o Schedule management plan
o Cost management plan
o Resource managementplan
o Risk managementplan
o Quality management plan
o Scopebaseline
o Schedulebaseline
o Cost baseline
Projectdocuments
o Assumption log
o Cost estimates
o Issue log
o Lessons learnedregister
o Requirementsdocumentation
o Resourcerequirements
o Stakeholder register
Agreements
Procurement documentation
Enterprise environmentalfactors
Organizational processassets
- Answer: B.
PMBOK® Guide, pages 437 - 438 , Section 11.5.3; and Figure 11 - 16
The Plan Risk Responses process has the following outputs:
Changerequests
Project management planupdates
o Schedulemanagement plan