+360-Questions-and-Answers-For-PMBOK-Guide-SIXTH -Edition

(khatib.arch2) #1
http://www.alsenosy.com | http://www.professionalengineers.us

o Cost management plan
o Quality management plan
o Resource managementplan
o Procurement managementplan
o Scopebaseline
o Schedulebaseline
o Cost baseline


Project documentsupdates


o Assumptionlog
o Cost forecasts
o Lessons learnedregister
o Projectschedule
o Riskregister


  1. Answer: D.


PMBOK® Guide, pages 428 - 432 , Section 11.4.2; and page 428 , Figure 11 - 11


The perform Quantitative Risk Analysis process has the following tools andtechniques:




  1. Expertjudgment




  2. Datagathering
    o Interviews




  3. Interpersonal and teamskills
    o Facilitation




  4. Representations of uncertainty




  5. Dataanalysis
    o Simulations
    o Sensitivity analysis
    o Decision Tree analysis
    o Influence diagrams




  6. Answer: A.




PMBOK® Guide, page 436 , Section 11.4.3; and page 428 , Figure 11 - 11


The Perform Quantitative Risk Analysis Process has the following outputs:


Project documentsupdates


o Riskreport
Free download pdf