o Cost management plan
o Quality management plan
o Resource managementplan
o Procurement managementplan
o Scopebaseline
o Schedulebaseline
o Cost baseline
Project documentsupdates
o Assumptionlog
o Cost forecasts
o Lessons learnedregister
o Projectschedule
o Riskregister
- Answer: D.
PMBOK® Guide, pages 428 - 432 , Section 11.4.2; and page 428 , Figure 11 - 11
The perform Quantitative Risk Analysis process has the following tools andtechniques:
Expertjudgment
Datagathering
o Interviews
Interpersonal and teamskills
o Facilitation
Representations of uncertainty
Dataanalysis
o Simulations
o Sensitivity analysis
o Decision Tree analysis
o Influence diagrams
Answer: A.
PMBOK® Guide, page 436 , Section 11.4.3; and page 428 , Figure 11 - 11
The Perform Quantitative Risk Analysis Process has the following outputs:
Project documentsupdates
o Riskreport