  1. Answer: C.


PMBOK® Guide, pages 411 - 412 , Section 11.2.1; and Figure 11 - 6


The Identify Risks process has the followinginputs:


Project managementplan


o Requirements management plan
o Schedule management plan
o Cost management plan
o Resource managementplan
o Risk managementplan
o Quality management plan
o Scopebaseline
o Schedulebaseline
o Cost baseline


Projectdocuments


o Assumption log
o Cost estimates
o Issue log
o Lessons learnedregister
o Requirementsdocumentation
o Resourcerequirements
o Stakeholder register


Agreements


Procurement documentation


Enterprise environmentalfactors


Organizational processassets



  1. Answer: B.


PMBOK® Guide, pages 437 - 438 , Section 11.5.3; and Figure 11 - 16


The Plan Risk Responses process has the following outputs:


Changerequests


Project management planupdates


o Schedulemanagement plan