248.Answer:A.


PMBOK® Guide, page 199 , Section 6.4.1.2; andGlossary


Resourcerequirements.Thetypesandquantitiesofresourcesrequiredforeachactivityinawork
package.


249.Answer:B.


PMBOK® Guide, page 19 , Section 1.2.4.1; andGlossary


Adaptive life cycle. A project life cycle that is iterative orincremental.


250.Answer:C.


PMBOK® Guide, page 200 , Section 6.4.2.2; andGlossary


Analogousestimating.Atechniqueforestimatingthedurationorcostofanactivityoraprojectusing
historicaldatafromasimilaractivityorproject.


251.Answer:D.


PMBOK®Guide,Glossary


Assumption.Afactorintheplanningprocessthatisconsideredtobetrue,real,orcertain;without
proofordemonstration.


252.Answer:A.


PMBOK® Guide, page 204 , Section 6.4.3.2; andGlossary


Basic of estimates. Supporting documentation outlining the details used in establishing project
estimatessuchasassumption,constraints,levelofdetail,range,andconfidencelevels.


253.Answer:B.


PMBOK® Guide, page 30 , Section 1.2.6.1; andGlossary


Businesscase.Adocumentedeconomicfeasibilitystudyusedtoestablishvalidityofthebenefitsofa
selectedcomponentlackingsufficientdefinitionandthatisusedasabasisfortheauthorizationof
furtherprojectmanagementactivities.


254.Answer:C.


PMBOK®Guide,Glossary


Checklistanalysis.Atechniqueforsystematicallyreviewingmaterialsusingalistforaccuracyand
completeness.