255.Answer:D.


PMBOK® Guide, pages 369 - 370 , Section 10.1.2.2; andGlossary


Communicationrequirementsanalysis.Ananalyticaltechniquetodeterminetheinformationneedsof
the project stakeholdersthrough interviews, workshops, study oflessonslearned from previous
projects,etc.


256.Answer:B.


PMBOK® Guide, page 245 , Section 7.2.2.6; andGlossary


Contingencyreserve.Timeormoneyallocatedinthescheduleorcostbaselineforknownriskswith
activeresponsestrategies.


257.Answer:B.


PMBOK® Guide, page 282 , Section 8.1.2.3; andGlossary


Costofquality(CoQ).Allcostsincurredoverthelifeoftheproductbyinvestmentinpreventing
nonconformance to requirement, appraisal of the product or service for conformance to
requirements,andfailurenomeetrequirements.


258.Answer:C.


PMBOK®Guide,Glossary


Critical path activity. Any activity on the critical path in a projectschedule.


259.Answer:D.


PMBOK® Guide, page 191 , Section 6.3.2.2; andGlossary


Totalfloat.Theamountoftimethatascheduleactivitycanbedelayedorextendedfromitsearly
startdatewithoutdelayingtheprojectfinishdateorviolatingascheduleconstraint.


260.Answer:A.


PMBOK® Guide, page 19 , Section 1.2.4.1; andGlossary


Incrementallifecycle.Anadaptiveprojectlifecycleinwhichthedeliverableisproducedthrougha
series ofiterations thatsuccessively add functionality within a predeterminedtime frame.The
deliverablecontainsthenecessaryandsufficientcapabilitytobeconsideredcompleteonlyafterthe
finaliteration.