261.Answer:B.


PMBOK® Guide, page 19 , Section 1.2.4.1; andGlossary


Iterativelifecycle.Anadaptiveprojectlifecycleinwhichthedeliverablematuresthroughaseriesof
repeatedcycles.Thedeliverablecontainsthenecessaryandsufficient capabilitytobeconsidered
completeat the end ofeach cycle.Each repeatedcyclefurther enhancesthe capability ofthe
deliverable.


262.Answer:C.


PMBOK® Guide, page 19 , Section 1.2.4.1; andGlossary


Predictivelife cycle. Aform ofproject life cyclein whichthe projectscope, time andcost are
determinedintheearlyphasesofthelifecycle.


263.Answer:D.


PMBOK® Guide, page 185 , Section 6.2.2.3; andGlossary


Progressiveelaboration.Theiterativeprocessofincreasingthelevelofdetailinaproject management
planasgreateramountsofinformationandmoreaccurateestimatesbecomeavailable.


264.Answer:A.


PMBOK® Guide, page 290 , Section 8.2; andGlossary


Qualityaudits.Aqualityauditisastructured,independentprocesstodetermineifprojectactivities
complywithorganizationalandprojectpolicies,processes,andprocedures.


265.Answer:B.


PMBOK® Guide, page 317 , Section 9.1.2.2; andGlossary


RACIchart.Acommontypeofresponsibilityassignmentmatrixthatusesresponsible,accountable,
consult,andinformstatuestodefinetheinvolvementofstakeholdersinprojectactivities.


266.Answer:C.


PMBOK® Guide, page 235 , Section 9.2.3.1; andGlossary


Requirementsdocumentation.Adescriptionofhowindividualrequirementsmeetthebusinessneed
fortheproject.