261.Answer:B.
PMBOK® Guide, page 19 , Section 1.2.4.1; andGlossary
Iterativelifecycle.Anadaptiveprojectlifecycleinwhichthedeliverablematuresthroughaseriesof
repeatedcycles.Thedeliverablecontainsthenecessaryandsufficient capabilitytobeconsidered
completeat the end ofeach cycle.Each repeatedcyclefurther enhancesthe capability ofthe
deliverable.
262.Answer:C.
PMBOK® Guide, page 19 , Section 1.2.4.1; andGlossary
Predictivelife cycle. Aform ofproject life cyclein whichthe projectscope, time andcost are
determinedintheearlyphasesofthelifecycle.
263.Answer:D.
PMBOK® Guide, page 185 , Section 6.2.2.3; andGlossary
Progressiveelaboration.Theiterativeprocessofincreasingthelevelofdetailinaproject management
planasgreateramountsofinformationandmoreaccurateestimatesbecomeavailable.
264.Answer:A.
PMBOK® Guide, page 290 , Section 8.2; andGlossary
Qualityaudits.Aqualityauditisastructured,independentprocesstodetermineifprojectactivities
complywithorganizationalandprojectpolicies,processes,andprocedures.
265.Answer:B.
PMBOK® Guide, page 317 , Section 9.1.2.2; andGlossary
RACIchart.Acommontypeofresponsibilityassignmentmatrixthatusesresponsible,accountable,
consult,andinformstatuestodefinetheinvolvementofstakeholdersinprojectactivities.
266.Answer:C.
PMBOK® Guide, page 235 , Section 9.2.3.1; andGlossary
Requirementsdocumentation.Adescriptionofhowindividualrequirementsmeetthebusinessneed
fortheproject.