information arestatus of deliverables,implementation status forchange requests, and forecast
estimatestocomplete.



  • Work performance reports. The physical or electronic representation of work performance
    informationcompiledinprojectdocuments,whichisintendedtogeneratedecisionsorraiseissues,
    actions,or awareness. Examplesincludestatusreports, memos, justifications,informationnotes,
    electronicdashboards,recommendations,andupdates.


Workperformanceanalysisisarequiredactivity,butnotasourceofprojectdata.


20 .Answer:A.


PMBOK®Guide,page 28 ,Section 1. 2. 5


Tailoringisnecessarybecauseeachprojectisunique;noteveryprocess,tool,technique,input,or
outputIdentifiedinthePMBOK®Guideisrequiredoneveryproject.Tailoringshouldaddressthe
competingconstraintsofscope,schedule,cost,resources,quality,andrisk.Theimportanceofeach
constraintisdifferentforeachproject,andtheprojectmanagertailorstheapproachformanaging
theseconstraintsbasedontheprojectenvironment,organizationalculture,stakeholderneeds,and
othervariables.


Intailoring projectmanagement, theprojectmanager shouldalsoconsiderthe varyinglevelsof
governancethatmayberequiredandwithinwhichtheprojectwilloperate,aswellasconsidering
thecultureoftheorganization.Inaddition,considerationofwhetherthecustomeroftheprojectis
internalorexternaltotheorganizationmayaffectprojectmanagementtailoringdecisions.


Butsincetailoringrequiressignificantprojectmanagementexperienceandknowledge,tailoringthe
projecttosuitaprojectmanager’sskillsetislikelytobeuncommon.