Palestine International Airport (Al-Auja)

(Noor Al-Dian Rabaya) #1
3

Left Taxiway Exits
* Earthworks including excavation and backfill of subgrade material.
* Flexible Pavement Works

3.1


Earthworks
1 - Excavation (Cut) m3 1,457,151 4 5,828,604
2 - Fill (Backfill imported from the site) m3 - 6 -

3.2


Flexible Pavement (40cm)
1 - HMA (25cm) m2 2,380 65 154,700
2 - Base Course(15cm) m3 17,424 40 696,960
Subtotal 7.531,924

4

Expansion of Apron Area
* Earthworks including excavation and backfill of subgrade material.
* Rigid Pavement Works

4.1


Earthworks
1 - Excavation (Cut) m3 128,985 4 515,940
2 - Fill (Backfill imported from the site) m3 139,847 6 839,082

4.2


Rigid Pavement (65cm)
1 - PCC (35 cm) m2 254,860 171 43,581,060
2 - HMA (15cm) m2 254,860 39 9,939,540
3 - Base Course(15cm) m3 38,229 40 1,529,160

4.3


Flexible Pavement for Apron Taxiways (40cm)
1 - HMA (25cm) m2 265,525 65 17,259,125
2 - Base Course(15cm) m3 39,830 40 1,593,200

Subtotal 75,257,107