234 APPENDIX A


Addendum #1



  1. Detail 16 on sheet S8.1 is a cross section of Detail 1 on
    sheet S8.1.

  2. Detail 7 on sheet S8.1 is a cross section of Detail 16 on
    sheet S8.1.

  3. The vertical rebar in Detail 13 on sheet S8.1 should be
    #5 in lieu of the #4 specified.

  4. In Detail 13 on sheet S8.1, provide #5, L-shaped dowels
    at 11 o.c. to connect foundation to the footing.

  5. Figure A.1 is to be used to construct the grade beam
    along the south wall of the building.


FIGURE A.1.Grade Beam Detail