technical NOTES

(Project Pridr) #1
S. N. Sub Location LED W LED Bat. Idle Hr/Mon

Energy
Cons
(KWh)

Total
Energy
Saving
(KwH)/
Month

Occupancy
Sensor
Required

7 Engineering Room 36 W 10 360 129.6 129.6 1
8 Inst. Workshop 36 W 5 360 64.8 64.8 1
9 Server Room 36 W 5 600 108 108 1
10 Robo Lab 36 W 16 120 69.12 69.12 1
11 Conf. Hall 36 W 19 600 410.4 410.4 2
Total Unit Consumption per month 10,827.52 59.00
Total Unit Consumption per Annum 1,29,930.24
Annual Saving 7,14,616.32


  • Note:

  • In all load centers, cable cellars & related rooms, Illumination on 24 hours in
    a day continuously, considering 3 hours’ average Occupancy in a day,
    remaining time, lighting fixtures should kept off & only emergency lights
    should be on, by using Occupancy sensors on load centers, we can save
    huge energy.

  • Saving for all Load Centers: Rs. 7,14,616/- Per Annum

  • ROI Calculation:

  • Pre Heater Building:
    At pre heater, from ground floor to top floor, Illumination on for 12 hours in
    a day from remote, we can save energy by using Occupancy sensors on
    ground floor with interlocking with other floor, so that, whenever, anybody
    will go for any work on Pre Heater building, he will switch on & perform
    work, considering 1 hours every day inspection in night hours basis, we can
    switch off 330 hours in a month for energy saving.


Equipment Detail Qty. UOM Cost per Qty. Total Cost

Overall
Cost
(INR)

Annual
Saving
(INR)

ROI
(Years)
Sensor 59 Nos. 7000 413000

Cable 2500 Mtr. (^100250000913000714616) 1.3
Erection Cost (Cable +
Sensor)^1 Set^250000250000