technical NOTES

(Project Pridr) #1

1.4 Costing Analysis of Various Projects


Description Unit Project 1 Project 2 Project 3 Project 4 Project 5 Project 6
Location Madhya Pradesh Odisha Chhattisgarh Odisha Maharashtra Maharashtra
Year 2017 2018 2020 2020 2018 2018
Sand Rs./ M3 1650 600 808 1053 1470 1470
Aggregate
10mm

Rs./ M3 610 1025 812 1593 635 635
Aggregate
20mm

Rs./ M3 640 1025 1021 1863 963 963
Excavation & Backfilling
0 to -3 m Rs./ M3 405 306 361 380 345 483
-3m to -6m Rs./ M3 585 333
-6 to -9m Rs./ M3 765 359
PCC 1:4:8 Rs./ M3 4100 3,945 4172 5000 5760 4360
RCC
upto 0m lvl Rs./ M3 4389 4,288 4700 6300 5650 4804
0 to +10m lvl Rs./ M3 4479 4,420 4850 5390 4630
10 to 20m lvl Rs./ M3 4794 4,550 5000 6468 5150
20 to 30m lvl Rs./ M3 4924 4,682 5150 6468 5150
30 to 40m lvl Rs./ M3 5059 4,813 5350 7595 5670
Shuttering
upto 0m lvl Rs./ M2 832 763 835 960 775 535
0 to +10m lvl Rs./ M2 945 891 986 1215 630
10 to 20m lvl Rs./ M2 990 1,017 1136 1215 630
20 to 30m lvl Rs./ M2 1039 1,145 1286 1215 630
30 to 40m lvl Rs./ M2 1089 1,364 1493 1509 800
Reinforcement
upto 0m lvl Rs./MT 9830 8,736 7978 27000 8310 11400
0 to +10m lvl Rs./MT 10347 8260 8635 11600
10 to 20m lvl Rs./MT 11382 8542
20 to 30m lvl Rs./MT 12417 8823
30 to 40m lvl Rs./MT 13451 9152 8960 11700
Overall
Contractor cost Rs./ M3 10614 8916 10863 13900 11616 9541
Cement Rs./ M3 RCC^168016801680168016801680
TMT Rs./ M3 RCC^585058505850585058505850
Total RCC Cost/
Cu.m

Rs./ M3
RCC

18144 16446 18393 21430 19146 17071
Average RCC
Cost

Rs./ M3
RCC^18438