Electric Power Generation, Transmission, and Distribution

(Tina Meador) #1

operation would not appear to be the result of loss of diversity but rather the high inrush currents. Since
inrush occurs during all energization and not just as a result of cold load pickup, it can be concluded
that cold load pickup is not a major factor in the application of FCIs.


Load Current

Fault
Current

Fault
Initiated

(Contacts
Closed)

2 s 2 s 2 s

Time

Reclosing Intervals
(Contacts Open)

"Fast" Operations
(Contacts Closed)

"Time Delay" Operations
(Contacts Closed)

Recloser
Lockout
(Contacts
Open)

Line Recloser

Dead Time

I sc Cycles^30 5 s 15 s 30 s

Current vs. Time
Feeder Breaker Reclosing

FIGURE 23.4 Reclosing sequences.


0

5

10

15

20

25

30

Transformers Laterals Feeders
Location

P.U. of Full Load

FIGURE 23.5 Magnitudes of inrush current.

Free download pdf