Architectural and Engineering Design Standards

(avery) #1
b. Alternator:

1) Output – 480/277 volts wye, 3 phase, 4 wire, 60 Hz, not less than 965 kW @ 80%
power factor load

2) Voltage Reguation – 1%


  1. Shop Drawings


Shop drawings on the engine-generator set shall be submitted for examination within thirty
(30) days after award of contract. Shop drawings shall include assembly drawings, equipment
specifications, wiring diagrams, piping diagrams, foundation and installation data, and
individual component drawings and data for such items as muffler, batteries, battery charger,
radiator, water pump, etc. NOTE: The size of the muffler and exhaust pipe required to keep
the back pressure within the manufacturer’s operating limits shall be submitted at the time of
bidding.



  1. Start-Up and Instructions


Upon completion of the installation of the set, a factory representative shall perform the
following: (Cost of such services shall be included with the proposal cost for the equipment.)


a. Inspect the installation to be sure that all components are properly installed and
connected.

b. Start-up and test all components of the set for proper operation. Prior to acceptance of
the equipment, the equipment shall be tested to show it is free of defects, will start
automatically and be subjected to full-load tests.

c. All tests shall be conducted at a time acceptable to the hospital and shall be conducted
with one or more of the UIHC representatives present as well as representatives of the
installing contractor.

d. Perform all performance adjustments as recommended by the manufacturer including,
but not limited to, valve adjustment, head bolt torquing, generator-engine alignment,
engine crankcase deflection, exhaust back pressure, and adjust oil pressure.

e. Operating and maintenance instruction books shall be supplied to hospital
representatives and procedures explained to the operating personnel.